Pincher Creek – 2016 Water Distribution Upgrades

Talbera provided to the Town of Pincher Creek planning, design, project management, utility coordination, and construction services to replace aging water mainline and to add additional water main looping in Pincher Creek, Alberta.
The scope of work included design, tendering, construction supervision, and project management for the replacement of 415 metres of aging water mainline by open trench construction, and the installation 100 metres of water mainline by directional drill under the Pincher Creek to allow for water looping under the Hewetson Avenue Bridge.